Project Management (Part III)
Поможем в ✍️ написании учебной работы
Поможем с курсовой, контрольной, дипломной, рефератом, отчетом по практике, научно-исследовательской и любой другой работой

Project Performance Measures. The traditional measures for judging project success are: scope, time, and budget. This is frequently depicted as a triangle.

Increasing any of the triangle's sides inherently changes at least one of the other sides. Thus, increasing the scope of the project will necessarily increase either the time required to complete the project or the budget allocated to the project. Unfortunately, the expanded scope can cause both time and budget to escalate simultaneously, as constrained resources come into conflict. Some project contracts have penalty clauses that elicit hefty payments if the project completion is past the contract date. Similarly, when the scope is decreased, the requisite time and budget may be reduced; resources may be assigned elsewhere.

 The triangle analogy breaks down when the time factor is reduced, i.e., the project completion date is moved up. An unexpected deadline change may necessitate the use of overtime resources. Overtime hours strain the budget, and may still be insufficient to complete the project within the specified time. Managers attempting to respond to deadline changes should note the relative costs of time-intensive expenses (such as weekly rental of equipment) and of resource-intensive expenses (wages).

 The schedule and budget are developed subsequent to the work breakdown structure, so that all activities and resources are identified. The budget is typically developed by estimating expenses at the bottom layer of the WBS, then rolling up the expenses to a project total. The numbering system in the WBS can be tailored to form a chart of accounts for tracking expenses associated with each activity.           The  project management  heading is  appropriate  under any of these

69

alternatives to ensure that staff salaries/wages are suitably allocated to the project. Earned value analysis incorporates both on-time and within-budget concepts of tracking the costs incurred to date on a project.

Roles in the Project Management Environment. Who is the customer of a project? Generally, the customer is the entity to which the deliverables are actually delivered. In an externally contracted project, the customer is easily identified. In an in-house project, the customer is the executive authorizing both the initiation of the project and the money allocated to it. In either case, the customer is the one with the right to complain when the performance measures of scope, time, and budget are not met.

Ideally, a project will have a sponsor, an intermediary between the customer and the project manager. This individual can help to define the scope for optimal delivery of results, to allocate appropriate funding, to resolve conflicts during the execution of the project.

The project manager is in charge of the work to be accomplished. This is not to say that the manager actually does the work, but rather that he/she is the coordinator of all relevant activities through delegation. In many cases, this manager may not possess expertise in the field, but rather possesses the skills to oversee a large number of diverse tasks and to identify the best-qualified employees to carry out the tasks. The manager should exercise judgment in assigning tasks; seasoned professionals will expect to accomplish the tasks according to their knowledge and experience, while others may require much definition and direction. In some cases, the project manager's ability to accomplish the job depends on negotiating and persuasive skills.

 Surrounding the project manager is a team with the goal of supporting the planning, directing, and controlling functions. Typically, a full-time (or nearly full-time) team member is assigned responsibility for traditional office functions, such as communication coordination. This member may also be in charge of fielding reports and recording the responses for comparison to the baseline schedule. Other members exercise delegated authority in project oversight, up to and including direct responsibility for sub-projects within the larger project context.

 

70

Exercises